Material not moving
-
Check intersections
- Material will not travel if there is not a path to follow
- If intersection is one-way material cannot flow back the other direction
-
Check material types
- Source type must match destination type
-
Check crushing plants
- Make sure source types and crushed types match with destination types.
- Check the quantity of each crushing plant.

Cut/fill doesn't match in Schedule mode
-
Check production rates
- May need to change production rates to match or add a local stockpile to the cut.
-
Check timing
- Make sure cut and fill are done at the same time or add a stockpile.
-
Check if material is hauled to disposal area instead of fill
- Check timing production rates and suitabilities.
- Check if disposal area has Must fill enabled.
-
Check crushing plants
- Make sure source types and crushed types match with destination types.
- Check the quantity of each crushing plant.
- Create more borrow pits or disposal areas
Task timing problems
- Make sure Schedule mode is active
-
Check task dependencies
- Dependencies causes changes in one to affect the timing of other tasks.
- Timing cannot be changed to break dependencies between other tasks.
-
Check crew and production rates
- Tasks cannot be completed without resources available
- Incorrect production rate coefficients can cause task to be done too slow or fast.
-
Check red flags
- A red flag on a task shows a timing constraint violation. Move your mouse over the flag to see the reason.
Cannot insert a stockpile
Stockpile is only active in Schedule and Control modes
- Change Project mode to Schedule mode or Control mode
- Select the Insert menu
- Select Stockpile
- Continue procedure as with a Borrow pit or Disposal area

Using Help
- Select the File menu
- Hover the mouse over Help
- Select View help from the sub-menu
- Select the Search box
- Type a keyword and press Enter
- Select link to view desired help page

Accessing the Assistant
- Type Assistant in DynaRoad Help search box
- Select the link for Control, Planning, or Scheduling assistant